All calculations run in your browser. Your inputs are never sent to any server.

Rebar Weight per Foot

Every bar size in lb/ft, where the number comes from, and what a scale says instead

← Back to the calculator
#4 rebar weighs 0.668 lb per foot, #6 weighs 1.502 and #8 weighs 2.670. Those are the nominal values in ASTM A615 — and clause 11.1 of the same standard accepts a bar at 94% of them, so the table is a definition, not a scale reading.

The per-foot figure is fixed by the bar designation, not by the bar in front of you: 0.668 for #4, 1.502 for #6, 2.670 for #8, straight out of the A615 column. The formulas further down reproduce that column — area × 12 × 0.2836 lb/in³ for steel, d² ÷ 162.2 in metric — but they are arithmetic, and this page labels them as arithmetic. Where a formula and the A615 table disagree, the A615 table is the number to use. How to check a stick on a scale is on the rebar measurement page.

But the weight that pays the invoice is not the steel in the slab — it is the steel you order, which also carries the laps and the offcut. Both are split out below.

Weight from size and length
#4 at 100 ft: 66.8 lb — 0.668 lb/ft, 0.994 kg/m

These are nominal values from ASTM A615, not a scale reading — for settlement and for ordering, use the measured weight on the mill certificate.

Order weight split into steel installed, laps and offcut What you pay for, and what you install 24 ft × 20 ft slab, #4 at 12 in, 20 ft bars Order 49 bars × 20 ft = 980 ft = 654.6 lb 626.6 lb installed 28 lb you buy on top of the net steel — 4.3% of the order 27.8 lb of that is laps (20 joints × 25 in) — steel you do install 0.2 lb is offcut at the end of the lines — steel you never place
One order, two numbers. The slab holds 626.6 lb of steel; the ticket says 654.6 lb. The gap is laps and offcut — small on the chart, but it is the whole reason an estimate that stops at net length comes up short.

Where the weight per foot comes from

Everything on this page comes out of these. The first two are exact; the third is the one you can do in your head.

Weight = length × weight per foot Imperial, from area = area (in²) × 3.403 lb/ft (exact, from steel density) Imperial, from bar no.= bar number² ÷ 24 lb/ft (estimate, good to ~1% for #3–#8) Metric = diameter² ÷ 162.2 kg/m (d in mm) Same length, different weight: #4 0.668 lb/ft 100 ft = 66.8 lb #6 1.502 lb/ft 100 ft = 150.2 lb 16 mm 1.578 kg/m 100 m = 157.8 kg Order weight = net weight + lap weight + offcut weight

The third line is the useful one: 4² ÷ 24 = 0.67 lb/ft. It works for any bar number up to about #8, and it is why doubling the bar number roughly quadruples the weight.

Which numbers are the standard's and which are arithmetic. Every lb/ft figure in the tables on this page is an ASTM A615 nominal value, copied. Everything in the box above is arithmetic on that table: 3.403 is 12 in/ft × 0.2836 lb/in³ of steel, and n² ÷ 24 is a rounded form of the same calculation, good to about 1% from #3 to #8. The #4 row shows why the two do not land on the same digit: A615 rounds the area to 0.20 in², the exact area is 0.1963 in², so 0.20 × 3.403 gives 0.681 while the table says 0.668. Use the table for anything that gets invoiced.

Does the coating change the weight per foot?

Not the number in the table. ASTM A615 fixes pounds per foot by bar designation, and footnote A to that table defines the nominal dimensions of a deformed bar as those of a plain round bar having the same weight per foot — so the figure is a definition attached to the designation, not a measurement of the bar you are holding. A #4 is 0.668 lb/ft in the table whether it is black, epoxy-coated or galvanised.

What the film does change is the outside diameter, because it sits on both sides of the bar:

film thickness t = 0.007 to 0.012 in per side (7 to 12 mil) coated OD = d + 2t film cross-section = π × t × (d + t) in² film area share = film area ÷ steel area ← area, not mass #4: t = 0.007 → OD 0.500 + 0.014 = 0.514 in t = 0.012 → OD 0.500 + 0.024 = 0.524 in film π × 0.007 × 0.507 = 0.0111 in² π × 0.012 × 0.512 = 0.0193 in²
BarNominal OD (in)Coated OD at 7 milCoated OD at 12 milFilm area at 7 mil (in²)Film area at 12 mil (in²)Film area vs steel area
#30.3750.3890.3990.00840.01467.6% / 13.2%
#40.5000.5140.5240.01110.01935.7% / 9.8%
#50.6250.6390.6490.01390.02404.5% / 7.8%
#60.7500.7640.7740.01660.02873.8% / 6.5%
#70.8750.8890.8990.01940.03343.2% / 5.6%
#81.0001.0141.0240.02210.03822.8% / 4.9%

Swipe the table sideways on a phone.

Coated OD is the nominal OD from ASTM A615 plus twice the A775 film thickness at 7 and 12 mil; film area is the coated circumference × length.

The last column is area, not weight, and the difference matters. Turning an area into a mass needs the density of the cured film, and cured epoxy is a good deal lighter than steel, so the mass share is smaller than the area share — not equal to it. This page does not have a sourced density for cured fusion-bonded epoxy, so the arithmetic stops at area and no weight percentage is quoted here. A percentage published without the density behind it is a guess wearing a number.

The 0.014 to 0.024 in is computed from the film, not measured on every bar. ASTM A775 accepts a coating when at least 90% of all recorded thickness measurements after curing are 7 to 12 mil, which means a bar can sit at the thin end of that band at one point and the thick end at another: one bar gains 0.014 in here and 0.024 in there. Read the coated-OD columns as the band a bar can fall in, not as a fixed size.

The film is also not the largest gap between the table and the scale. A615 evaluates bars on nominal weight and accepts a measured weight at 94% of the nominal value — 0.628 lb/ft on a #4 — and adds that overweight shall in no case be a cause for rejection. A 6% band on the scale is wider than anything a 12 mil film does to a 0.500 in diameter.

Weight per foot, size by size

The five sizes that cover most residential and light commercial work. The complete chart — every imperial size from #3 to #18 and metric 10 mm to 40 mm, with areas and bars per ton — is in the rebar weight chart below; the rebar size and weight chart adds diameters and areas.

Barlb / ft20 ft bar (lb)40 ft bar (lb)lb per 100 ft
#30.3767.515.037.6
#40.66813.426.766.8
#51.04320.941.7104.3
#61.50230.060.1150.2
#82.67053.4106.8267.0

Swipe the table sideways for more columns →

lb/ft is the nominal ASTM A615 value; the 20 ft, 40 ft and 100 ft columns are that value × length, not a scale reading.

Sizekg / m12 m bar (kg)kg per 100 m
10 mm0.6177.461.7
12 mm0.88810.788.8
16 mm1.57818.9157.8
20 mm2.46629.6246.6
25 mm3.85346.2385.3

Swipe the table sideways for more columns →

How much rebar do I need per square foot?

For a square grid, a one-foot square of slab holds one foot of bar in each direction — two feet of bar in total. So the weight per square foot is just 2 ÷ spacing × weight per foot, and at 24 in spacing it is the weight per foot itself.

Barlb / ft12 in16 in18 in24 in
#30.3760.7520.5640.5010.376
#40.6681.3361.0020.8910.668
#51.0432.0861.5641.3911.043
#61.5023.0042.2532.0031.502
#82.6705.3404.0053.5602.670

Swipe the table sideways for more columns →

Read it as pounds of rebar per square foot of slab. A #4 grid at 12 in on centre is 1.336 lb/sq ft; the same #4 at 18 in drops to 0.891 lb/sq ft.

For a whole pour rather than a square foot — bars, feet and pounds for a patio, shed, garage, driveway or walkway slab — the how much rebar do I need page runs the same arithmetic row by row.

Pounds of rebar per square foot against the spacing: doubling the spacing halves the steel lb per square foot is just 2 ÷ spacing × lb per ft four bar sizes, four spacings — every column halves as the spacing doubles 12 in 16 in 18 in 24 in 32 in #4 1.336 1.002 0.891 0.668 0.501 #5 2.086 1.564 1.391 1.043 0.782 #6 3.004 2.253 2.003 1.502 1.127 Same shape every time 12 in → 24 in is double the spacing and exactly half the steel: #4 goes 1.336 → 0.668 lb/sq ft. The bar size moves the whole row up and down; the spacing scales it along the row. Values from the table above. Example bar sizes shown; any size follows the same rule.
Pounds of rebar per square foot, drawn as bars against the spacing. Every row has the same shape because the steel is proportional to 1 ÷ spacing; the bar size only sets the height of the row. Doubling the spacing from 12 in to 24 in halves the figure exactly.
This is a shortcut, and it runs about 2% high. It assumes the grid covers the whole slab, but the bars stop short of the edge by the cover. Checked against the exact grid on the 24 ft × 20 ft slab used above: the shortcut gives 480 × 1.336 = 641.3 lb, the exact takeoff gives 626.6 lb — 2.3% more than you need. Use it to size a job in your head, then run the real grid before you order. It also excludes laps and offcut, which is what the rebar estimator covers.

Worked example: from a takeoff to pounds

A 24 ft × 20 ft slab, #4 bar at 12 in on centre, 3 in edge clearance, 20 ft stock bars. The takeoff gives 938 ft of steel in the slab and 49 bars to order. Here is what each part weighs.

PartLengthWorkingWeight
Steel in the slab938 ft938 × 0.668626.6 lb
Laps (20 laps × 25 in)41.7 ft41.67 × 0.66827.8 lb
Offcut (49 bars = 980 ft)0.3 ft0.33 × 0.6680.2 lb
Order weight980 ft980 × 0.668654.6 lb

Swipe the table sideways for more columns →

The three parts add to 654.6 lb exactly. You pay for 654.6 lb and you install 626.6 lb. The 28 lb difference is laps and offcut — 4.3% of the order, and it is real money at any price per pound.

Net weight versus order weight for the same slab: 580.5 lb of steel bought as 1,122 lb or 842 lb depending on stock length The same steel, three different purchase weights 24 ft x 20 ft slab, #4 at 12 in o.c., 3/4 in cover 0 600 lb 1,200 lb 580.5 lb net weight steel in the slab 842 lb order, 30 ft stock 42 bars 1,122 lb order, 20 ft stock 84 bars +93% over net
Three numbers for one slab. The net weight is what the finished grid holds. The order weight is what you pay for, and it depends on the stock length you buy: 30 ft bars halve the piece count and drop the order from 1,122 lb to 842 lb, even though the steel in the slab never changes. This is why the quote and the takeoff rarely match.

The three weights, and which one you are being quoted

All the figures on this site are nominal: they come from the bar designation through ASTM A615, not from a bar on a scale. A coating does not change the nominal figure — the film sits outside the nominal diameter, and what it adds to the measured diameter is worked out above. What moves the scale is the rolling tolerance, and clause 11.1 puts its floor at 94% of nominal.

If weight is the payment basis, use the mill certificate, not a calculator. Nominal weight is the right number for estimating, ordering and comparing quotes. It is not a certified weight for settlement. Where the two disagree, the certificate and your contract govern.

Cost from weight

Yards quote either per bar or per pound, and the two are not interchangeable — a per-bar price already carries the offcut, a per-pound price does not. Convert with one multiplication:

Cost = order weight (lb) × price per lb Cost = bars ordered × price per bar

Take the 654.6 lb order above. At a quoted $0.85 per pound it is $556; at $1.10 per pound it is $720. Substitute your own quote — the point is that a 4.3% weight difference between two takeoffs is a 4.3% difference in the bill, so it is worth getting the laps right before you order rather than after.

A per-bar and a per-pound quote are only comparable once both are in the same unit, and the same is true of the per-foot, per-hundredweight and per-ton quotes a yard may hand you. The rebar price per foot page converts all five units to one dollars-per-pound figure, and shows why a price per foot cannot be compared across bar sizes at all.

Metric: kilograms per metre

The metric rule is shorter than the imperial one and just as easy to do in your head: kg/m = d² ÷ 162.2, with d in millimetres.

16 mm : 16 × 16 = 256 ÷ 162.2 = 1.578 kg/m 20 mm : 20 × 20 = 400 ÷ 162.2 = 2.466 kg/m 25 mm : 25 × 25 = 625 ÷ 162.2 = 3.853 kg/m

A standard 12 m bar is the length that matters in metric markets, so 16 mm bar is 18.9 kg per stick and about 52 sticks to the tonne. The full metric table, including areas and bars per tonne, is on the size and weight chart.

#4 rebar weight

#4 is the size most people search for by name, so here it is on its own:

Measure#4 (0.500 in / 12.7 mm)
Per foot0.668 lb
Per 20 ft stick13.4 lb
Per 40 ft stick26.7 lb
Per 100 ft66.8 lb
Per metre0.994 kg
40 ft bars per tonabout 74
Feet per tonabout 2,994 ft

Swipe the table sideways for more columns →

Two independent routes agree here, which is a good way to check any rebar weight: 0.668 lb/ft × 1.4882 = 0.994 kg/m, and 12.7² ÷ 162.2 = 0.994 kg/m. Same bar, two formulas, 0.03% apart.

Rebar weight chart — every size from #3 to #18, in one table

A rebar weight chart is the lookup table behind every weight number on this page: every imperial size from #3 to #18 and every metric size from 10 mm to 40 mm, in the four numbers a yard actually quotes — pounds per foot (mill certificates and per-pound pricing), pounds per full bar (what you lift, load and strap down), bars per ton (what you order), and kilograms per metre (metric drawings). The nominal weights are the ASTM A615 values, calculated from the bar designation and the density of steel, not measured off a bar.

weight per foot (imperial) = area (in²) × 12 × 0.2836 lb/in³ #4: 0.1963 × 12 × 0.2836 = 0.668 lb/ft weight per metre (metric) = d² (mm) ÷ 162.2 16 mm: 256 ÷ 162.2 = 1.578 kg/m bars per short ton = floor( 2000 ÷ (lb/ft × stock length) )

Three numbers to read first: #4 is 0.668 lb/ft, a 20 ft #4 bar is 13.4 lb, and a short ton holds 149 of them on 20 ft stock. Everything below is the same three numbers for every size.

Barlb / ftkg / m20 ft bar (lb)40 ft bar (lb)Bars / short ton (20 ft)Bars / short ton (40 ft)
#30.3760.5607.515.0265132
#40.6680.99413.426.714974
#51.0431.55220.941.79547
#61.5022.23530.060.16633
#72.0443.04240.981.84824
#82.6703.97353.4106.83718
#93.4005.06068.0136.02914
#104.3036.40486.1172.12311
#115.3137.907106.3212.5189
#147.65011.384153.0306.0136
#1813.60020.239272.0544.073

Swipe the table sideways for more columns →

Nominal ASTM A615 weights, #3 to #18. kg/m is the same bar converted; 20 ft and 40 ft are the stock lengths sold in the US.

The bars-per-ton column is rounded down, not to the nearest whole bar: 96 twenty-foot #5 bars weigh 2,002.6 lb, which is over a short ton, so a ton buys 95. That is the same floor rule the tonnage page uses when it turns a tonnage target into a purchase order.

Metrickg / mlb / ft12 m bar (kg)6 m bar (kg)Bars / tonne (12 m)
10 mm0.6170.4157.43.7135
12 mm0.8880.59710.75.393
16 mm1.5781.06018.99.552
20 mm2.4661.65729.614.833
25 mm3.8532.58946.223.121
28 mm4.8343.24958.029.017
32 mm6.3134.24275.837.913
40 mm9.8646.629118.459.28

Swipe the table sideways for more columns →

Metric side of the same chart: kg/m is the nominal metric unit weight; 12 m and 6 m are the stock lengths sold outside the US.

Each column answers a different question. Pounds per foot is what mill certificates and per-pound pricing run on — 1,000 ft of #5 is 1,043 lb of steel whatever length you buy it in. Pounds per full bar is what you lift, load and strap down — a 20 ft #4 is a one-hand lift at 13.4 lb, while a single 40 ft #18 bar is 544.0 lb and needs equipment. Bars per ton is what the yard invoices on when the order is placed by weight. And kg/m is what a metric drawing hands you.

The rebar weight chart drawn: pounds per foot (left panel) and the weight of a full 20 ft bar (right panel) for every imperial size #3 to #18 Pounds per foot A full 20 ft bar weighs #3 #4 #5 #6 #7 #8 #9 #10 #11 #14 #18 #3 #4 #5 #6 #7 #8 #9 #10 #11 #14 #18 0.376 0.668 1.043 1.502 2.044 2.670 3.400 4.303 5.313 7.650 13.600 7.5 13.4 20.9 30.0 40.9 53.4 68.0 86.1 106.3 153.0 272.0 Square-root scale: #18 carries 36× the steel of #3, and on a straight scale every bar under #8 would be a sliver. The right panel is the left one stretched by exactly 20 — that is all a stock length does. Amber is #4, the size most residential work orders. Labels are the exact chart values.
The weight chart drawn: pounds per foot on the left, the full 20 ft bar on the right, for every imperial size. The metric sizes follow the same shape — a 40 mm bar is 9.864 kg/m, sixteen times a 10 mm bar — and the tables above carry the exact numbers.

Work the chart in the direction the quote goes. Two short tons of #5 on 20 ft stock: the chart says #5 is 1.043 lb/ft, so a 20 ft bar is 20.9 lb, and 2,000 ÷ 20.9 = 95.8 — rounded down to 95 whole bars. Those 95 bars are 1,900 ft = 1,981.7 lb = 0.99 short tons. Order the 96th bar and you have bought 2,002.6 lb, two and a half pounds over the ton you were quoted.

Two things the chart will not do. It is nominal weight — the mill certificate settles a payment, because rolling tolerance moves a real bar by a fraction of a percent. And the mental shortcut bar number² ÷ 24 only matches the chart up to #8 (within 0.3%); by #11 it reads 5.1% light, which is exactly the drift the measurement page traces to the same root cause. For anything above #8, read the table.

Horizontal chart of the error from using bar number squared divided by 24 against the exact chart weight, for #3 to #18: #3 to #8 sit inside 0.3 percent, #10 reads 3.2 percent light, #11 reads 5.1 percent light and #14 reads 6.8 percent heavy Where the “bar number² ÷ 24” shortcut drifts Error against the exact chart weight, by bar size. Left of the line the shortcut reads light; right of it, heavy. -6% -4% -2% +2% +4% +6% 0 #3 #4 #5 #6 #7 #8 #9 -0.7% #10 -3.2% #11 -5.1% #14 +6.8% #18 -0.7% all six inside 0.3% — the rule is usable here
The shortcut drawn against the chart. From #3 to #8 every point sits inside 0.3% of the exact value, which is why the rule is taught and why it works on the sizes residential work actually buys: the bar number is a diameter in eighths and the weight follows the area, so the fit is nearly exact. Past #8 the nominal diameters stop being eighths — #9 is 1.128 in, not 1.125, and #14 is 1.693 in, not 1.750 — and the error turns into a real number: 5.1% light at #11 and 6.8% heavy at #14. On a two-ton order that is 136 lb, or about ten #4 bars, decided by which formula you used.

Watch: the rebar weight chart

16-second walkthrough: the rebar weight chart row by row, the three questions each column answers (pricing, handling, ordering), and why a short ton buys 95 twenty-foot #5 bars instead of 96. From the rebarcount channel.

Common questions

How much does rebar weigh per foot?

#4 weighs 0.668 lb per foot, #5 is 1.043, #6 is 1.502 and #8 is 2.670. For any imperial size #3 to #8 the quick estimate is the bar number squared divided by 24, so 4² = 16, divided by 24 gives 0.67 lb per foot. In metric, kilograms per metre = diameter² ÷ 162.2, so a 16 mm bar is 1.578 kg/m.

How much does a #4 rebar weigh?

A #4 bar weighs 0.668 lb per foot. That is 13.4 lb for a 20 ft stick and 26.7 lb for a 40 ft stick, and roughly 74 forty-foot bars to a ton. The metric equivalent, 12.7 mm, comes out at 0.994 kg/m, so the two systems agree to within 0.05%.

Why is the weight I order more than the weight in the slab?

Because you buy whole bars. The steel in the slab is the net length, and on top of that you carry the laps where bars join and the offcut left at the end of each line. On a 24 ft × 20 ft slab with 20 ft bars, 626.6 lb of steel in the slab becomes a 654.6 lb order: 27.8 lb of laps and 0.2 lb of offcut.

How do I convert rebar weight between pounds and kilograms?

One pound per foot is 1.4882 kilograms per metre, so 0.668 lb/ft is 0.994 kg/m. Going the other way, one kilogram per metre is 0.6720 pounds per foot. For the same nominal bar the two systems agree to within 0.05%.

What is on a rebar weight chart?

Every rebar size in one table — imperial #3 through #18 and metric 10 mm through 40 mm — with the four numbers a yard quotes: pounds per foot, kilograms per metre, the weight of a full stock bar (20 ft and 40 ft, or 12 m and 6 m), and how many whole bars fit in a ton. The anchor row is #4: 0.668 lb/ft, 13.4 lb per 20 ft stick, 149 bars per short ton on 20 ft stock. Read the per-foot column for pricing, the per-bar column for handling, and the per-ton column when the order is placed by weight. The full chart is in the rebar weight chart section above.

Does epoxy coating change rebar weight per foot?

Not the nominal weight. ASTM A615 fixes pounds per foot by bar designation, so a #4 is 0.668 lb/ft coated or black. What the film changes is the outside diameter: 7 to 12 mil on both sides adds 0.014 to 0.024 in, taking a #4 from 0.500 to 0.514–0.524 in. The film cross-section on a #4 is 0.0111 to 0.0193 in², which is 5.7% to 9.8% of the bar's 0.1963 in² steel area — area, not mass. Converting that to a weight percentage needs the density of the cured film, which this page does not carry, so no percentage is quoted.

How far below nominal can a rebar weigh and still pass?

To 94% of the ASTM A615 value. ASTM A615 evaluates bars on nominal weight and requires the measured weight of the test specimen to be at least 94% of the tabulated weight per unit length, which on a #4 is 0.628 lb/ft. The same clause says overweight shall in no case be a cause for rejection. A 6% band on the scale is wider than anything a 12 mil coating does to a 0.500 in diameter.

What this page does not do

It does not weigh your steel. Every figure here is nominal — calculated from the bar designation and standard steel density, not measured. It does not put a weight percentage on the epoxy or galvanised coating — that needs the density of the cured film, and the page gives the film’s area instead — it does not deduct for bends, and it does not model the mill tolerance beyond the 94% floor in clause 11.1. It also does not design anything: bar size, spacing and lap class are engineering decisions. For a weight that settles a payment, use the mill certificate.
Open the Rebar Calculator → Free, no login, runs in your browser

Published 2 October 2026 · Last reviewed 1 November 2026